N84 Grid

Norwich Main 400kV Substation

NESO connection site, host NGET.

Contracted here4.54 GWNot yet connected, as printed
Entries in the queue8entries with a printed MW
Earliest connection date18 Dec 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue4,107 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Norwich31 May 202418 Dec 202557 MW
Hornsea Power Station 331 May 20241 Oct 20262,250 MW
Hornsea Power Station 331 May 202431 Dec 2028750 MW
Scira-Dudgeon Extension31 May 20241 Jan 2030719 MW
Scira-Dudgeon Extension31 May 202431 Oct 2031231 MW
Norwich 100MW BESS31 May 202431 Oct 2031100 MW
Norwich 231 May 202430 Jun 203328 MW
Scira-Dudgeon Extension31 May 20241 Oct 2034400 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.5 GW5.0 GW2025: 57 MW2026: 2.3 GW2028: 3.1 GW2030: 3.8 GW2031: 4.1 GW2033: 4.1 GW2034: 4.5 GW2025202720292031203320344.5 GW
0 MW2.5 GW5.0 GW2025: 57 MW2026: 2.3 GW2028: 3.1 GW2030: 3.8 GW2031: 4.1 GW2033: 4.1 GW2034: 4.5 GW20252028203120344.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202557 MW
20262,307 MW
20283,057 MW
20303,776 MW
20314,107 MW
20334,135 MW
20344,535 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Norwich57 MW0 MW18 Dec 2025not statedgate not printedConsents Approved
2Hornsea Power Station 32,250 MW57 MW1 Oct 2026not statedgate not printedConsents Approved
3Hornsea Power Station 3750 MW2,307 MW31 Dec 2028not statedgate not printedConsents Approved
4Scira-Dudgeon Extension719 MW3,057 MW1 Jan 2030not statedgate not printedScoping
5Scira-Dudgeon Extension231 MW3,776 MW31 Oct 2031not statedgate not printedScoping
6Norwich 100MW BESS100 MW4,007 MW31 Oct 2031not statedgate not printedScoping
7Norwich 228 MW4,107 MW30 Jun 20331gate 1Scoping
8Scira-Dudgeon Extension400 MW4,135 MW1 Oct 2034not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025157 MW
202612,250 MW
20281750 MW
20301719 MW
20312331 MW
2033128 MW
20341400 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Hornsea Power Station 3Hybrid3,000 MW31 Dec 2028Consents Approved
Scira-Dudgeon ExtensionOffshore wind1,350 MW1 Oct 2034Scoping
Great YarmouthGas420 MWnot statedBuilt
Norwich 100MW BESSBattery storage100 MW31 Oct 2031Scoping
NorwichHybrid57 MW18 Dec 2025Consents Approved
Norwich 2Hybrid28 MW30 Jun 2033Scoping
Project YareHybrid0 MW25 Oct 2024Awaiting Consents

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.