N84 Grid

Nursling 400kV Substation

NESO connection site, host NGET.

Contracted here2.98 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Oct 2037Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,980 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
NatPower Nursling Energy Park31 May 202431 Oct 20371,000 MW
EPL Hampshire20 Dec 202431 Oct 2037480 MW
Nursling Flexible Generation22 Jul 202530 Oct 20381,500 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2037: 1.5 GW2038: 3.0 GW203720383.0 GW
0 MW2.0 GW4.0 GW2037: 1.5 GW2038: 3.0 GW203720383.0 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20371,480 MW
20382,980 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1NatPower Nursling Energy Park1,000 MW0 MW31 Oct 2037not statedgate not printedScoping
2EPL Hampshire480 MW1,000 MW31 Oct 20371gate 1Scoping
3Nursling Flexible Generation1,500 MW1,480 MW30 Oct 2038not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203721,480 MW
203811,500 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Nursling Flexible GenerationGas1,500 MW30 Oct 2038Scoping
NatPower Nursling Energy ParkBattery storage1,000 MW31 Oct 2037Scoping
EPL HampshireHybrid480 MW31 Oct 2037Scoping
Nursling TertiaryBattery storage49.9 MWnot statedBuilt
Peak Gen SouthamptonGas24 MWnot statedBuilt
Peak Gen FarehamGas21 MWnot statedBuilt
Conrad (Winchester) LimitedHybrid19 MWnot statedBuilt