The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Monets Garden
31 May 2024 to 8 Jun 2027 (gate 2) - Osbaldwick PV & BESS Sub
31 May 2024 to 30 Aug 2033 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Monets Garden | 31 May 2024 | 8 Jun 2027 | 57 MW |
| Osbaldwick PV & BESS Sub | 31 May 2024 | 30 Aug 2033 | 249.9 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 57 MW |
| 2033 | 306.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Monets Garden | 57 MW | 0 MW | 8 Jun 2027 | 2 | gate 2 | Consents Approved |
| 2 | Osbaldwick PV & BESS Sub | 249.9 MW | 57 MW | 30 Aug 2033 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 1 | 57 MW |
| 2033 | 1 | 249.9 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Osbaldwick PV & BESS Sub | Hybrid | 249.9 MW | 30 Aug 2033 | Scoping |
| Monets Garden | Battery storage | 57 MW | 8 Jun 2027 | Consents Approved |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.