Osbaldwick 400kV Substation

NESO connection site, host NGET.

Contracted here0.31 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date8 Jun 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue306.9 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Monets Garden31 May 20248 Jun 202757 MW
Osbaldwick PV & BESS Sub31 May 202430 Aug 2033249.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2027: 57 MW2033: 307 MW2027202820292030203120322033307 MW
0 MW200 MW400 MW2027: 57 MW2033: 307 MW2027202920312033307 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202757 MW
2033306.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Monets Garden57 MW0 MW8 Jun 20272gate 2Consents Approved
2Osbaldwick PV & BESS Sub249.9 MW57 MW30 Aug 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2027157 MW
20331249.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Osbaldwick PV & BESS SubHybrid249.9 MW30 Aug 2033Scoping
Monets GardenBattery storage57 MW8 Jun 2027Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.