N84 Grid

Overton 275kV

NESO connection site, host NGET.

Contracted here2.43 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date1 Jun 2032Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,425 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Overton Solar & Storage Farm31 May 20241 Jun 20321,400 MW
Overton Green Energy Centre31 May 202424 Oct 20351,025 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.3 GW2.5 GW2032: 1.4 GW2035: 2.4 GW20322033203420352.4 GW
0 MW1.3 GW2.5 GW2032: 1.4 GW2035: 2.4 GW20322033203420352.4 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20321,400 MW
20352,425 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Overton Solar & Storage Farm1,400 MW0 MW1 Jun 2032not statedgate not printedScoping
2Overton Green Energy Centre1,025 MW1,400 MW24 Oct 2035not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203211,400 MW
203511,025 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Overton Solar & Storage FarmHybrid1,400 MW1 Jun 2032Scoping
Overton Green Energy CentreHybrid1,025 MW24 Oct 2035Awaiting Consents

Supported by National Energy SO Open Data