N84 Grid

Penrhos GSP

NESO connection site, host NGET.

Contracted here0.39 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date30 Oct 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue390 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Recell at Penrhos (BEGA)31 May 202430 Oct 2025150 MW
Recell at Penrhos (BEGA)31 May 202431 Oct 202760 MW
Menter Mon Morlais Anglesey Marine Energy31 May 202431 Mar 202840 MW
Menter Mon Morlais Anglesey Marine Energy31 May 202431 Mar 202920 MW
Menter Mon Morlais Anglesey Marine Energy31 May 202431 Mar 203040 MW
Menter Mon Morlais Anglesey Marine Energy31 May 202431 Mar 203280 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2025: 150 MW2027: 210 MW2028: 250 MW2029: 270 MW2030: 310 MW2032: 390 MW20252026202720282029203020312032390 MW
0 MW200 MW400 MW2025: 150 MW2027: 210 MW2028: 250 MW2029: 270 MW2030: 310 MW2032: 390 MW2025202720292032390 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2025150 MW
2027210 MW
2028250 MW
2029270 MW
2030310 MW
2032390 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Recell at Penrhos (BEGA)150 MW0 MW30 Oct 2025not statedgate not printedConsents Approved
2Recell at Penrhos (BEGA)60 MW150 MW31 Oct 2027not statedgate not printedConsents Approved
3Menter Mon Morlais Anglesey Marine Energy40 MW210 MW31 Mar 2028not statedgate not printedUnder Construction/Commissioning
4Menter Mon Morlais Anglesey Marine Energy20 MW250 MW31 Mar 2029not statedgate not printedUnder Construction/Commissioning
5Menter Mon Morlais Anglesey Marine Energy40 MW270 MW31 Mar 2030not statedgate not printedUnder Construction/Commissioning
6Menter Mon Morlais Anglesey Marine Energy80 MW310 MW31 Mar 2032not statedgate not printedUnder Construction/Commissioning

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20251150 MW
2027160 MW
2028140 MW
2029120 MW
2030140 MW
2032180 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Recell at Penrhos (BEGA)Biomass and waste210 MW31 Oct 2027Consents Approved
Menter Mon Morlais Anglesey Marine EnergyTidal and wave180 MW31 Mar 2032Under Construction/Commissioning

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.