Pentir 400kV Substation

NESO connection site, host NGET.

Contracted here1.08 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,082 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Fferm Solar Pentir31 May 202431 Oct 202857 MW
Pentir Green Energy Centre31 May 202430 Oct 20371,025 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2028: 57 MW2037: 1.1 GW2028203020322034203620371.1 GW
0 MW1.0 GW2.0 GW2028: 57 MW2037: 1.1 GW20282031203420371.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202857 MW
20371,082 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Fferm Solar Pentir57 MW0 MW31 Oct 20282gate 2Consents Approved
2Pentir Green Energy Centre1,025 MW57 MW30 Oct 20371gate 1Awaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028157 MW
203711,025 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Pentir Green Energy CentreHybrid1,025 MW30 Oct 2037Awaiting Consents
Fferm Solar PentirBattery storage57 MW31 Oct 2028Consents Approved
DolgarrogHydro and pumped storage39 MWnot statedBuilt

Supported by National Energy SO Open Data