The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Persley Croft BESS
31 May 2024 to 30 Jul 2026, date already passed (gate 2) - Persley BESS
7 Nov 2025 to 31 Jul 2027 (gate 2)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Persley Croft BESS | 31 May 2024 | 30 Jul 2026 | 50 MW |
| Persley BESS | 7 Nov 2025 | 31 Jul 2027 | 63.3 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 50 MW |
| 2027 | 113.3 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Persley Croft BESS | 50 MW | 0 MW | 30 Jul 2026 | 2 | gate 2 | Under Construction/Commissioning |
| 2 | Persley BESS | 63.3 MW | 50 MW | 31 Jul 2027 | 2 | gate 2 | Consents Approved |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 50 MW |
| 2027 | 1 | 63.3 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Persley BESS | Battery storage | 63.3 MW | 31 Jul 2027 | Consents Approved |
| Persley Croft BESS | Battery storage | 50 MW | 30 Jul 2026 | Under Construction/Commissioning |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.