N84 Grid

Peterhead 400kV Substation

NESO connection site, host SHET.

Contracted here5.62 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date1 Mar 2030Date printed in the register

The queue, in order

Order calculated by N84
First in queue4,270 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
NorthConnect15 Feb 20221 Mar 20301,400 MW
Salamander Offshore Wind Farm31 May 202431 Mar 2030200 MW
Buchan 01 Offshore Wind Farm31 May 202431 Oct 2033960 MW
Peterhead Battery31 May 202431 Oct 2033500 MW
Stirling BESS27 Sep 202431 Oct 2033300 MW
Peterhead Carbon Capture31 May 202431 Oct 2033910 MW
CENOS31 May 202431 Oct 20351,350 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW4.0 GW8.0 GW2030: 1.6 GW2033: 4.3 GW2035: 5.6 GW2030203120322033203420355.6 GW
0 MW4.0 GW8.0 GW2030: 1.6 GW2033: 4.3 GW2035: 5.6 GW20302032203420355.6 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20301,600 MW
20334,270 MW
20355,620 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1NorthConnect1,400 MW0 MW1 Mar 2030not statedgate not printedScoping
2Salamander Offshore Wind Farm200 MW1,400 MW31 Mar 2030not statedgate not printedScoping
3Buchan 01 Offshore Wind Farm960 MW1,600 MW31 Oct 2033not statedgate not printedScoping
4Peterhead Battery500 MW2,560 MW31 Oct 20331gate 1Scoping
5Stirling BESS300 MW3,060 MW31 Oct 20331gate 1Scoping
6Peterhead Carbon Capture910 MW3,360 MW31 Oct 2033not statedgate not printedScoping
7CENOS1,350 MW4,270 MW31 Oct 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Interconnector Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203021,600 MW
203342,670 MW
203511,350 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
NorthConnectInterconnector1,400 MW1 Mar 2030Scoping
CENOSOffshore wind1,350 MW31 Oct 2035Scoping
Peterhead (SSE THERMAL GENERATION (SCOTLAND) LIMITED)Gas1,180 MWnot statedBuilt
Buchan 01 Offshore Wind FarmOffshore wind960 MW31 Oct 2033Scoping
Peterhead Carbon CaptureGas910 MW31 Oct 2033Scoping
Peterhead BatteryBattery storage500 MW31 Oct 2033Scoping
Stirling BESSBattery storage300 MW31 Oct 2033Scoping
Salamander Offshore Wind FarmHybrid200 MW31 Mar 2030Scoping
White Cairns BESSBattery storage0 MWnot statedScoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.