Quantans Hill 132kV Substation

NESO connection site, host SPT.

Contracted here0.15 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date2 Jul 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue145 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Quantans Hill Wind Farm31 May 20242 Jul 202995 MW
Cornharrow Wind Farm31 May 202431 Oct 203050 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2029: 95 MW2030: 145 MW20292030145 MW
0 MW100 MW200 MW2029: 95 MW2030: 145 MW20292030145 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202995 MW
2030145 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Quantans Hill Wind Farm95 MW0 MW2 Jul 2029not statedgate not printedScoping
2Cornharrow Wind Farm50 MW95 MW31 Oct 2030not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2029195 MW
2030150 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Quantans Hill Wind FarmOnshore wind95 MW2 Jul 2029Scoping
Cornharrow Wind FarmOnshore wind50 MW31 Oct 2030Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.