N84 Grid

Rannoch GSP

NESO connection site, host SHET.

Contracted here0.02 GWNot yet connected, as printed
Entries in the queue1entry with a printed MW
Earliest connection date31 Oct 2035Date printed in the register

The queue, in order

Order calculated by N84
First in queue20 MW across the first project
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Talladh a Bheithe31 May 2024 to 31 Oct 2035 (gate 1)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Talladh a Bheithe31 May 202431 Oct 203520 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW10 MW20 MW2035: 20 MW203520 MW
0 MW10 MW20 MW2035: 20 MW203520 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
203520 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Talladh a Bheithe20 MW0 MW31 Oct 20351gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2035120 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Rannoch (SSE GENERATION LIMITED)Hydro and pumped storage44 MWnot statedBuilt
Talladh a BheitheBattery storage20 MW31 Oct 2035Scoping
Corrour Hydro Generating StationHydro and pumped storage5.5 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.