N84 Grid

Rayleigh 400kV Substation

NESO connection site, host NGET.

Contracted here1.53 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 Jun 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,530 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Gresham House Rayleigh BESS31 May 202430 Jun 2028480 MW
Bradwell Energy Park31 May 202431 Oct 2032499 MW
Bradwell Energy Park31 May 202431 Oct 2034551 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2028: 480 MW2032: 979 MW2034: 1.5 GW20282029203020312032203320341.5 GW
0 MW1.0 GW2.0 GW2028: 480 MW2032: 979 MW2034: 1.5 GW20282030203220341.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028480 MW
2032979 MW
20341,530 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Gresham House Rayleigh BESS480 MW0 MW30 Jun 2028not statedgate not printedScoping
2Bradwell Energy Park499 MW480 MW31 Oct 2032not statedgate not printedScoping
3Bradwell Energy Park551 MW979 MW31 Oct 2034not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20281480 MW
20321499 MW
20341551 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Bradwell Energy ParkHybrid1,050 MW31 Oct 2034Scoping
Gresham House Rayleigh BESSBattery storage480 MW30 Jun 2028Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.