Redmoss GSP

NESO connection site, host SHET.

Contracted here0.07 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Mar 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue67.8 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Rigifa BESS SEL7 Nov 2025 to 31 Mar 2026, date already passed (gate 2)
  • Redmoss GSP7 Nov 2025 to 31 Jul 2026, date already passed (gate not printed)
  • Kincorth BESS22 Jul 2025 to 31 Oct 2031 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Rigifa BESS SEL7 Nov 202531 Mar 202640 MW
Redmoss GSP7 Nov 202531 Jul 20268 MW
Kincorth BESS22 Jul 202531 Oct 203119.8 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW40 MW80 MW2026: 48 MW2031: 68 MW20262027202820292030203168 MW
0 MW40 MW80 MW2026: 48 MW2031: 68 MW202620282030203168 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202648 MW
203167.8 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Rigifa BESS SEL40 MW0 MW31 Mar 20262gate 2Consents Approved
2Redmoss GSP8 MW40 MW31 Jul 2026not statedgate not printedScoping
3Kincorth BESS19.8 MW48 MW31 Oct 2031not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026248 MW
2031119.8 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Kincardine Offshore Wind FarmOffshore wind49.6 MWnot statedBuilt
Rigifa BESS SELBattery storage40 MW31 Mar 2026Consents Approved
Kincorth BESSBattery storage19.8 MW31 Oct 2031Scoping
NESS Energy ProjectBiomass and waste16 MWnot statedBuilt
Redmoss GSP (Scottish Hydro Electric Power Distribution Plc)Battery storage8 MW31 Jul 2026Scoping

Supported by National Energy SO Open Data