N84 Grid

Redshaw 132kV Substation.

NESO connection site, host SPT.

Contracted here1.12 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Oct 2036Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,124 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Hagshaw LDES22 Jul 202531 Oct 2036500 MW
High Netherfauld Farm BESS22 Jul 202531 Oct 2037504 MW
Clyde South Energy Park22 Jul 202531 Oct 2037120 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2036: 500 MW2037: 1.1 GW203620371.1 GW
0 MW1.0 GW2.0 GW2036: 500 MW2037: 1.1 GW203620371.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2036500 MW
20371,124 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Hagshaw LDES500 MW0 MW31 Oct 2036not statedgate not printedScoping
2High Netherfauld Farm BESS504 MW500 MW31 Oct 2037not statedgate not printedScoping
3Clyde South Energy Park120 MW1,004 MW31 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20361500 MW
20372624 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
High Netherfauld Farm BESSBattery storage504 MW31 Oct 2037Scoping
Hagshaw LDESBattery storage500 MW31 Oct 2036Scoping
Clyde South Energy ParkHybrid120 MW31 Oct 2037Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.