N84 Grid

Rhigos 400kV Substation

NESO connection site, host NGET.

Contracted here1.08 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date13 Dec 2030Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,081 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Nant Aman31 May 2024 to 13 Dec 2030 (gate 1)
  • Tarenni31 May 2024 to 13 Dec 2030 (gate 1)
  • East Pit31 May 2024 to 15 Oct 2037 (gate 1)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Nant Aman31 May 202413 Dec 2030143 MW
Tarenni31 May 202413 Dec 2030188 MW
East Pit31 May 202415 Oct 2037750 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2030: 331 MW2037: 1.1 GW203020312032203320342035203620371.1 GW
0 MW1.0 GW2.0 GW2030: 331 MW2037: 1.1 GW20302032203420371.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2030331 MW
20371,081 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Nant Aman143 MW0 MW13 Dec 20301gate 1Scoping
2Tarenni188 MW143 MW13 Dec 20301gate 1Scoping
3East Pit750 MW331 MW15 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20302331 MW
20371750 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
East PitHybrid750 MW15 Oct 2037Scoping
Hirwaun Power StationGas299 MWnot statedBuilt
Pen Y Cymoedd Wind FarmOnshore wind228 MWnot statedBuilt
TarenniOnshore wind188 MW13 Dec 2030Scoping
Nant AmanOnshore wind143 MW13 Dec 2030Scoping
Rhigos BESSBattery storage0 MW31 Oct 2037Scoping