Richborough 400kV Substation

NESO connection site, host NGET.

Contracted here0.30 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Apr 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue298.95 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Sheaf Energy31 May 202430 Apr 2025249 MW
Harrington Franklin Limited27 Sep 202431 Oct 202549.95 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2025: 299 MW2025299 MW
0 MW200 MW400 MW2025: 299 MW2025299 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2025298.95 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Sheaf Energy249 MW0 MW30 Apr 2025not statedgate not printedConsents Approved
2Harrington Franklin Limited49.95 MW249 MW31 Oct 2025not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20252298.95 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Nemo LinkInterconnector1,020 MWnot statedBuilt
Sheaf EnergyBattery storage249 MW30 Apr 2025Consents Approved
Richborough 2 (RICHBOROUGH ENERGY PARK LIMITED)Battery storage50 MWnot statedBuilt
Richborough 1 (RICHBOROUGH ENERGY PARK LIMITED)Battery storage50 MWnot statedBuilt
Harrington Franklin LimitedBattery storage49.95 MW31 Oct 2025Awaiting Consents
TINZ Nene 4 (Richborough)Reactive compensation0 MW30 May 2025Scoping
Tamar-RichboroughReactive compensation0 MW31 Oct 2025Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.