Rochdale 132kV Substation

NESO connection site, host NGET.

Contracted here0.23 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Oct 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue227 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Rochdale BESS31 May 202430 Oct 202957 MW
Calderdale Wind Farm 240 MW22 Jul 202530 Oct 2037170 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2029: 57 MW2037: 227 MW20292031203320352037227 MW
0 MW125 MW250 MW2029: 57 MW2037: 227 MW2029203220352037227 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202957 MW
2037227 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Rochdale BESS57 MW0 MW30 Oct 20292gate 2Consents Approved
2Calderdale Wind Farm 240 MW170 MW57 MW30 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2029157 MW
20371170 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Calderdale Wind Farm 240 MWOnshore wind170 MW30 Oct 2037Scoping
Rochdale BESSBattery storage57 MW30 Oct 2029Consents Approved
Green Frog @ Goose House LaneGas21 MWnot statedBuilt

Supported by National Energy SO Open Data