The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Rochdale BESS
31 May 2024 to 30 Oct 2029 (gate 2) - Calderdale Wind Farm 240 MW
22 Jul 2025 to 30 Oct 2037 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Rochdale BESS | 31 May 2024 | 30 Oct 2029 | 57 MW |
| Calderdale Wind Farm 240 MW | 22 Jul 2025 | 30 Oct 2037 | 170 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2029 | 57 MW |
| 2037 | 227 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Rochdale BESS | 57 MW | 0 MW | 30 Oct 2029 | 2 | gate 2 | Consents Approved |
| 2 | Calderdale Wind Farm 240 MW | 170 MW | 57 MW | 30 Oct 2037 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2029 | 1 | 57 MW |
| 2037 | 1 | 170 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Calderdale Wind Farm 240 MW | Onshore wind | 170 MW | 30 Oct 2037 | Scoping |
| Rochdale BESS | Battery storage | 57 MW | 30 Oct 2029 | Consents Approved |
| Green Frog @ Goose House Lane | Gas | 21 MW | not stated | Built |
Supported by National Energy SO Open Data