N84 Grid

Rothienorman 2 400/33KV GSP Substation

NESO connection site, host SHET.

Contracted here0.12 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Oct 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue115.9 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Overhill BESS31 May 2024 to 31 Oct 2024, date already passed (gate not printed)
  • Rothienorman 3 BESS7 Nov 2025 to 30 Jun 2030 (gate 1)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Overhill BESS31 May 202431 Oct 202449.9 MW
Rothienorman 3 BESS7 Nov 202530 Jun 203066 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2024: 50 MW2030: 116 MW2024202520262027202820292030116 MW
0 MW100 MW200 MW2024: 50 MW2030: 116 MW2024202620282030116 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202449.9 MW
2030115.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Overhill BESS49.9 MW0 MW31 Oct 2024not statedgate not printedConsents Approved
2Rothienorman 3 BESS66 MW49.9 MW30 Jun 20301gate 1Scoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2024149.9 MW
2030166 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Rothienorman 3 BESSBattery storage66 MW30 Jun 2030Scoping
Overhill BESSBattery storage49.9 MW31 Oct 2024Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.