N84 Grid

Ryhall 400kV Substation

NESO connection site, host NGET.

Contracted here0.79 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date1 Jan 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue790 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Essendine31 May 20241 Jan 2028240 MW
Graeme Road Solar & BESS31 May 202430 Oct 2038550 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2028: 240 MW2038: 790 MW202820302032203420362038790 MW
0 MW400 MW800 MW2028: 240 MW2038: 790 MW2028203120342038790 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028240 MW
2038790 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Essendine240 MW0 MW1 Jan 2028not statedgate not printedConsents Approved
2Graeme Road Solar & BESS550 MW240 MW30 Oct 2038not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20281240 MW
20381550 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Graeme Road Solar & BESSHybrid550 MW30 Oct 2038Scoping
EssendineSolar240 MW1 Jan 2028Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.