N84 Grid

Saltcoats 132/33kV

NESO connection site, host SPT.

Contracted here0.13 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date21 Aug 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue130 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Meiklelaught Farm BESS31 May 202421 Aug 202830 MW
Saltcoats NEP BESS Facility31 May 202431 Oct 2029100 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2028: 30 MW2029: 130 MW20282029130 MW
0 MW100 MW200 MW2028: 30 MW2029: 130 MW20282029130 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202830 MW
2029130 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Meiklelaught Farm BESS30 MW0 MW21 Aug 2028not statedgate not printedScoping
2Saltcoats NEP BESS Facility100 MW30 MW31 Oct 2029not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028130 MW
20291100 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Saltcoats NEP BESS FacilityBattery storage100 MW31 Oct 2029Awaiting Consents
Meiklelaught Farm BESSBattery storage30 MW21 Aug 2028Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.