N84 Grid

SEABANK 400/33kV SUBSTATION

NESO connection site, host NGET.

Contracted here0.18 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date1 Nov 2023Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue184.9 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Seabank (Tertiary)31 May 20241 Nov 202349.9 MW
Severn Road Avonmouth31 May 202431 Oct 2038135 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2023: 50 MW2038: 185 MW20232025202720292031203320352038185 MW
0 MW100 MW200 MW2023: 50 MW2038: 185 MW20232027203120352038185 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202349.9 MW
2038184.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Seabank (Tertiary)49.9 MW0 MW1 Nov 20231gate 1Awaiting Consents
2Severn Road Avonmouth135 MW49.9 MW31 Oct 2038not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2023149.9 MW
20381135 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Seabank (SEABANK POWER LIMITED)Gas1,234 MWnot statedBuilt
Severn Road AvonmouthHybrid135 MW31 Oct 2038Scoping
Seabank (Tertiary)Battery storage49.9 MW1 Nov 2023Awaiting Consents

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.