Sellindge 400kV Substation

NESO connection site, host NGET.

Contracted here0.58 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue576 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Sellindge (Tertiary)31 May 202431 Oct 202849.9 MW
Sellindge (Tertiary)31 May 202431 Oct 203126.1 MW
Partridge Farm BESS31 May 202431 Oct 2037500 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2028: 50 MW2031: 76 MW2037: 576 MW202820302032203420362037576 MW
0 MW400 MW800 MW2028: 50 MW2031: 76 MW2037: 576 MW2028203120342037576 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202849.9 MW
203176 MW
2037576 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Sellindge (Tertiary)49.9 MW0 MW31 Oct 2028not statedgate not printedAwaiting Consents
2Sellindge (Tertiary)26.1 MW49.9 MW31 Oct 2031not statedgate not printedAwaiting Consents
3Partridge Farm BESS500 MW76 MW31 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028149.9 MW
2031126.1 MW
20371500 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
IFA InterconnectorInterconnector1,988 MWnot statedBuilt
ElecLinkInterconnector1,000 MWnot statedBuilt
Partridge Farm BESSBattery storage500 MW31 Oct 2037Scoping
Sellindge (Tertiary)Battery storage76 MW31 Oct 2031Awaiting Consents
SevingtonGas10 MWnot statedBuilt
Sellindge Grid Stability ServicesReactive compensation0 MW11 Aug 2026Consents Approved

Supported by National Energy SO Open Data