The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Allt an Tuir Renewable Energy Park
31 May 2024 to 30 Jun 2031 (gate not printed) - Meall Buidhe Wind Farm
20 Dec 2024 to 31 Oct 2032 (gate not printed) - Strath Oykel Wind Farm
21 Mar 2025 to 31 Oct 2032 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Allt an Tuir Renewable Energy Park | 31 May 2024 | 30 Jun 2031 | 50 MW |
| Meall Buidhe Wind Farm | 20 Dec 2024 | 31 Oct 2032 | 40 MW |
| Strath Oykel Wind Farm | 21 Mar 2025 | 31 Oct 2032 | 74 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2031 | 50 MW |
| 2032 | 164 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Allt an Tuir Renewable Energy Park | 50 MW | 0 MW | 30 Jun 2031 | not stated | gate not printed | Scoping |
| 2 | Meall Buidhe Wind Farm | 40 MW | 50 MW | 31 Oct 2032 | not stated | gate not printed | Scoping |
| 3 | Strath Oykel Wind Farm | 74 MW | 90 MW | 31 Oct 2032 | not stated | gate not printed | Awaiting Consents |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2031 | 1 | 50 MW |
| 2032 | 2 | 114 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Strath Oykel Wind Farm | Hybrid | 74 MW | 31 Oct 2032 | Awaiting Consents |
| Allt an Tuir Renewable Energy Park | Hybrid | 50 MW | 30 Jun 2031 | Scoping |
| Meall Buidhe Wind Farm | Onshore wind | 40 MW | 31 Oct 2032 | Scoping |
| Rosehall | Onshore wind | 24.7 MW | not stated | Built |
| Shin (SSE GENERATION LIMITED) | Hydro and pumped storage | 18.6 MW | not stated | Built |