Shrewsbury 400kV Substation

NESO connection site, host NGET.

Contracted here0.48 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Sep 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue480.84 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
JBM Solar 12 - Shrewsbury Solar31 May 202430 Sep 202849.99 MW
Kenwick Solar27 Mar 202630 Oct 2037430.85 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW250 MW500 MW2028: 50 MW2037: 481 MW202820302032203420362037481 MW
0 MW250 MW500 MW2028: 50 MW2037: 481 MW2028203120342037481 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202849.99 MW
2037480.84 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1JBM Solar 12 - Shrewsbury Solar49.99 MW0 MW30 Sep 2028not statedgate not printedScoping
2Kenwick Solar430.85 MW49.99 MW30 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028149.99 MW
20371430.85 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Kenwick SolarSolar430.85 MW30 Oct 2037Scoping
JBM Solar 12 - Shrewsbury SolarHybrid49.99 MW30 Sep 2028Scoping
Shropshire Energy ParkHybrid0 MWnot statedScoping

Supported by National Energy SO Open Data