N84 Grid

Smeaton 400/275kV

NESO connection site, host SPT.

Contracted here0.53 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Jul 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue528 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Smeaton BESS31 May 202431 Jul 2028228 MW
Crossgatehall BESS21 Mar 202528 Oct 2033300 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2028: 228 MW2033: 528 MW202820292030203120322033528 MW
0 MW400 MW800 MW2028: 228 MW2033: 528 MW2028203020322033528 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028228 MW
2033528 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Smeaton BESS228 MW0 MW31 Jul 20282gate 2Consents Approved
2Crossgatehall BESS300 MW228 MW28 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20281228 MW
20331300 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Crossgatehall BESSBattery storage300 MW28 Oct 2033Scoping
Smeaton BESSBattery storage228 MW31 Jul 2028Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.