South Anglia Connection Node A 400kV Substation

NESO connection site, host NGET.

Contracted here1.24 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Oct 2034Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,240 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Lightsource Bramford PV & BESS31 May 202430 Oct 2034240 MW
Alcemi Bramford Battery Energy Storage Facility Phase 227 Sep 202431 Oct 20341,000 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2034: 1.2 GW20341.2 GW
0 MW1.0 GW2.0 GW2034: 1.2 GW20341.2 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20341,240 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Lightsource Bramford PV & BESS240 MW0 MW30 Oct 20341gate 1Scoping
2Alcemi Bramford Battery Energy Storage Facility Phase 21,000 MW240 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203421,240 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Alcemi Bramford Battery Energy Storage Facility Phase 2Battery storage1,000 MW31 Oct 2034Scoping
Lightsource Bramford PV & BESSHybrid240 MW30 Oct 2034Scoping

Supported by National Energy SO Open Data