The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Rat Hall Mod App
31 May 2024 to 31 Oct 2032 (gate 1) - Lacey's Farm BESS
31 May 2024 to 31 Oct 2033 (gate 1) - Coryton
31 May 2024 to 31 Oct 2034 (gate 1) - Rat Hall Mod App
31 May 2024 to 31 Oct 2034 (gate 1) - NatPower Tilbury Green Energy Park
20 Dec 2024 to 31 Oct 2034 (gate 1) - Cold Norton
31 May 2024 to 31 Oct 2036 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Rat Hall Mod App | 31 May 2024 | 31 Oct 2032 | 200 MW |
| Lacey's Farm BESS | 31 May 2024 | 31 Oct 2033 | 924 MW |
| Coryton | 31 May 2024 | 31 Oct 2034 | 1,000 MW |
| Rat Hall Mod App | 31 May 2024 | 31 Oct 2034 | 500 MW |
| NatPower Tilbury Green Energy Park | 20 Dec 2024 | 31 Oct 2034 | 1,000 MW |
| Cold Norton | 31 May 2024 | 31 Oct 2036 | 1,250 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2032 | 200 MW |
| 2033 | 1,124 MW |
| 2034 | 3,624 MW |
| 2036 | 4,874 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Rat Hall Mod App | 200 MW | 0 MW | 31 Oct 2032 | 1 | gate 1 | Scoping |
| 2 | Lacey's Farm BESS | 924 MW | 200 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
| 3 | Coryton | 1,000 MW | 1,124 MW | 31 Oct 2034 | 1 | gate 1 | Scoping |
| 4 | Rat Hall Mod App | 500 MW | 2,124 MW | 31 Oct 2034 | 1 | gate 1 | Scoping |
| 5 | NatPower Tilbury Green Energy Park | 1,000 MW | 2,624 MW | 31 Oct 2034 | 1 | gate 1 | Scoping |
| 6 | Cold Norton | 1,250 MW | 3,624 MW | 31 Oct 2036 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2032 | 1 | 200 MW |
| 2033 | 1 | 924 MW |
| 2034 | 3 | 2,500 MW |
| 2036 | 1 | 1,250 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Cold Norton | Hybrid | 1,250 MW | 31 Oct 2036 | Scoping |
| NatPower Tilbury Green Energy Park | Battery storage | 1,000 MW | 31 Oct 2034 | Scoping |
| Coryton | Solar | 1,000 MW | 31 Oct 2034 | Scoping |
| Lacey's Farm BESS | Battery storage | 924 MW | 31 Oct 2033 | Scoping |
| Rat Hall Mod App | Hybrid | 700 MW | 31 Oct 2034 | Scoping |