N84 Grid

South Anglia Connection Node C 400kV Substation

NESO connection site, host NGET.

Contracted here4.87 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date31 Oct 2032Date printed in the register

The queue, in order

Order calculated by N84
First in queue4,874 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Rat Hall Mod App31 May 202431 Oct 2032200 MW
Lacey's Farm BESS31 May 202431 Oct 2033924 MW
Coryton31 May 202431 Oct 20341,000 MW
Rat Hall Mod App31 May 202431 Oct 2034500 MW
NatPower Tilbury Green Energy Park20 Dec 202431 Oct 20341,000 MW
Cold Norton31 May 202431 Oct 20361,250 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.5 GW5.0 GW2032: 200 MW2033: 1.1 GW2034: 3.6 GW2036: 4.9 GW203220332034203520364.9 GW
0 MW2.5 GW5.0 GW2032: 200 MW2033: 1.1 GW2034: 3.6 GW2036: 4.9 GW2032203420364.9 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2032200 MW
20331,124 MW
20343,624 MW
20364,874 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Rat Hall Mod App200 MW0 MW31 Oct 20321gate 1Scoping
2Lacey's Farm BESS924 MW200 MW31 Oct 20331gate 1Scoping
3Coryton1,000 MW1,124 MW31 Oct 20341gate 1Scoping
4Rat Hall Mod App500 MW2,124 MW31 Oct 20341gate 1Scoping
5NatPower Tilbury Green Energy Park1,000 MW2,624 MW31 Oct 20341gate 1Scoping
6Cold Norton1,250 MW3,624 MW31 Oct 20361gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20321200 MW
20331924 MW
203432,500 MW
203611,250 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Cold NortonHybrid1,250 MW31 Oct 2036Scoping
NatPower Tilbury Green Energy ParkBattery storage1,000 MW31 Oct 2034Scoping
CorytonSolar1,000 MW31 Oct 2034Scoping
Lacey's Farm BESSBattery storage924 MW31 Oct 2033Scoping
Rat Hall Mod AppHybrid700 MW31 Oct 2034Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.