N84 Grid

South Anglia Connection Node D 400kV Substation

NESO connection site, host NGET.

Contracted here1.40 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Oct 2030Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,400 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Sunnica31 May 202431 Oct 2030500 MW
Church Road Farm22 Jul 202531 Oct 2034400 MW
Cambridgeshire Energy Storage Centre22 Jul 202531 Oct 2037500 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2030: 500 MW2034: 900 MW2037: 1.4 GW203020312032203320342035203620371.4 GW
0 MW1.0 GW2.0 GW2030: 500 MW2034: 900 MW2037: 1.4 GW20302032203420371.4 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2030500 MW
2034900 MW
20371,400 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Sunnica500 MW0 MW31 Oct 2030not statedgate not printedConsents Approved
2Church Road Farm400 MW500 MW31 Oct 20341gate 1Scoping
3Cambridgeshire Energy Storage Centre500 MW900 MW31 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20301500 MW
20341400 MW
20371500 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Cambridgeshire Energy Storage CentreHybrid500 MW31 Oct 2037Scoping
SunnicaHybrid500 MW31 Oct 2030Consents Approved
Church Road FarmBattery storage400 MW31 Oct 2034Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.