South Anglia Connection Node E 400kV Substation

NESO connection site, host NGET.

Contracted here1.51 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Oct 2034Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,508.9 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Red House Farm - Friston 400kV 249MW connection31 May 202431 Oct 2034249 MW
PVDP Woodbridge22 Jul 202531 Oct 2034610 MW
Lime Tree Energy Park31 May 202431 Oct 2034249.9 MW
Woodbridge - Noventum22 Jul 202531 Oct 2034400 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2034: 1.5 GW20341.5 GW
0 MW1.0 GW2.0 GW2034: 1.5 GW20341.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20341,508.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Red House Farm - Friston 400kV 249MW connection249 MW0 MW31 Oct 2034not statedgate not printedScoping
2PVDP Woodbridge610 MW249 MW31 Oct 2034not statedgate not printedScoping
3Lime Tree Energy Park249.9 MW859 MW31 Oct 2034not statedgate not printedScoping
4Woodbridge - Noventum400 MW1,108.9 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203441,508.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
PVDP WoodbridgeHybrid610 MW31 Oct 2034Scoping
Woodbridge - NoventumBattery storage400 MW31 Oct 2034Scoping
Lime Tree Energy ParkHybrid249.9 MW31 Oct 2034Scoping
Red House Farm - Friston 400kV 249MW connectionBattery storage249 MW31 Oct 2034Scoping

Supported by National Energy SO Open Data