N84 Grid

South Wales West Connection Node B 400kV Substation

NESO connection site, host NGET.

Contracted here0.70 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Oct 2036Date printed in the register

The queue, in order

Order calculated by N84
First in queue700 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Baglan BESS IPC27 Sep 2024 to 31 Oct 2036 (gate 1)
  • Galileo 1522 Jul 2025 to 6 Dec 2036 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Baglan BESS IPC27 Sep 202431 Oct 2036500 MW
Galileo 1522 Jul 20256 Dec 2036200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2036: 700 MW2036700 MW
0 MW400 MW800 MW2036: 700 MW2036700 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2036700 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Baglan BESS IPC500 MW0 MW31 Oct 20361gate 1Scoping
2Galileo 15200 MW500 MW6 Dec 2036not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20362700 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Baglan BESS IPCBattery storage500 MW31 Oct 2036Scoping
Galileo 15Battery storage200 MW6 Dec 2036Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.