N84 Grid

Spennymoor 400kV Substation

NESO connection site, host NGET.

Contracted here0.85 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue849.7 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Spennymoor31 May 202431 Oct 202849.9 MW
Spennymoor PV & BESS31 May 202430 Jul 203249.9 MW
Spennymoor Greener Grid Park31 May 202430 Oct 2035500 MW
Spennymoor PV & BESS Sub31 May 202430 Oct 2035249.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2028: 50 MW2032: 100 MW2035: 850 MW20282029203020312032203320342035850 MW
0 MW500 MW1.0 GW2028: 50 MW2032: 100 MW2035: 850 MW2028203020322035850 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202849.9 MW
203299.8 MW
2035849.7 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Spennymoor49.9 MW0 MW31 Oct 20281gate 1Awaiting Consents
2Spennymoor PV & BESS49.9 MW49.9 MW30 Jul 2032not statedgate not printedScoping
3Spennymoor Greener Grid Park500 MW99.8 MW30 Oct 2035not statedgate not printedScoping
4Spennymoor PV & BESS Sub249.9 MW599.8 MW30 Oct 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028149.9 MW
2032149.9 MW
20352749.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Spennymoor Greener Grid ParkBattery storage500 MW30 Oct 2035Scoping
Spennymoor PV & BESS SubHybrid249.9 MW30 Oct 2035Scoping
Spennymoor PV & BESSHybrid49.9 MW30 Jul 2032Scoping
Spennymoor (PIVOTED POWER LLP)Battery storage49.9 MW31 Oct 2028Awaiting Consents

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.