N84 Grid

Spittal 132kV Substation

NESO connection site, host SHET.

Contracted here1.06 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Oct 2030Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,062 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Balvedavist 162 Battery Storage31 May 202431 Oct 2030162 MW
Spittal BESS31 May 202431 Oct 2030300 MW
SSE Spittal Energy Park31 May 202431 Oct 2033600 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2030: 462 MW2033: 1.1 GW20302031203220331.1 GW
0 MW1.0 GW2.0 GW2030: 462 MW2033: 1.1 GW20302031203220331.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2030462 MW
20331,062 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Balvedavist 162 Battery Storage162 MW0 MW31 Oct 2030not statedgate not printedAwaiting Consents
2Spittal BESS300 MW162 MW31 Oct 20301gate 1Scoping
3SSE Spittal Energy Park600 MW462 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20302462 MW
20331600 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
SSE Spittal Energy ParkHybrid600 MW31 Oct 2033Scoping
Spittal BESSBattery storage300 MW31 Oct 2030Scoping
Balvedavist 162 Battery StorageHybrid162 MW31 Oct 2030Awaiting Consents
Acha Energy StorageBattery storage0 MWnot statedScoping
SPITTAL MAINS BATTERY ENERGY STORAGEBattery storage0 MWnot statedScoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.