The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Orchard BESS
31 May 2024 to 30 Oct 2037 (gate 1) - Ebstree Road BESS
27 Sep 2024 to 30 Oct 2037 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Orchard BESS | 31 May 2024 | 30 Oct 2037 | 100 MW |
| Ebstree Road BESS | 27 Sep 2024 | 30 Oct 2037 | 150 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2037 | 250 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Orchard BESS | 100 MW | 0 MW | 30 Oct 2037 | 1 | gate 1 | Scoping |
| 2 | Ebstree Road BESS | 150 MW | 100 MW | 30 Oct 2037 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2037 | 2 | 250 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Ebstree Road BESS | Battery storage | 150 MW | 30 Oct 2037 | Scoping |
| Orchard BESS | Battery storage | 100 MW | 30 Oct 2037 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.