The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Pentland Road
7 Nov 2025 to 31 Dec 2030 (gate 2) - Druim Leathann BEGA
31 May 2024 to 31 Mar 2027 (gate not printed) - Battery Point BESS
31 May 2024 to 31 Oct 2030 (gate not printed) - Beinn Thulabaigh Wind
7 Nov 2025 to 31 Oct 2033 (gate not printed) - West Coast Community Energy
7 Nov 2025 to 31 Oct 2033 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Pentland Road | 7 Nov 2025 | 31 Dec 2030 | 4.2 MW |
| Druim Leathann BEGA | 31 May 2024 | 31 Mar 2027 | 49.7 MW |
| Battery Point BESS | 31 May 2024 | 31 Oct 2030 | 25 MW |
| Beinn Thulabaigh Wind | 7 Nov 2025 | 31 Oct 2033 | 6 MW |
| West Coast Community Energy | 7 Nov 2025 | 31 Oct 2033 | 44 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 49.7 MW |
| 2030 | 78.9 MW |
| 2033 | 128.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Pentland Road | 4.2 MW | 0 MW | 31 Dec 2030 | 2 | gate 2 | Under Construction/Commissioning |
| 2 | Druim Leathann BEGA | 49.7 MW | 4.2 MW | 31 Mar 2027 | not stated | gate not printed | Scoping |
| 3 | Battery Point BESS | 25 MW | 53.9 MW | 31 Oct 2030 | not stated | gate not printed | Scoping |
| 4 | Beinn Thulabaigh Wind | 6 MW | 78.9 MW | 31 Oct 2033 | not stated | gate not printed | Scoping |
| 5 | West Coast Community Energy | 44 MW | 84.9 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 1 | 49.7 MW |
| 2030 | 2 | 29.2 MW |
| 2033 | 2 | 50 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Druim Leathann BEGA | Onshore wind | 49.7 MW | 31 Mar 2027 | Scoping |
| West Coast Community Energy | Onshore wind | 44 MW | 31 Oct 2033 | Scoping |
| Battery Point BESS | Battery storage | 25 MW | 31 Oct 2030 | Scoping |
| Stornoway (Battery Point) | Thermal | 22.3 MW | not stated | Built |
| Pentland Road | Onshore wind | 18 MW | 31 Dec 2030 | Under Construction/Commissioning |
| Beinn Thulabaigh Wind | Onshore wind | 6 MW | 31 Oct 2033 | Scoping |
Supported by National Energy SO Open Data