N84 Grid

Stornoway GSP

NESO connection site, host SHET.

Contracted here0.13 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date31 Mar 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue128.9 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Pentland Road7 Nov 202531 Dec 20304.2 MW
Druim Leathann BEGA31 May 202431 Mar 202749.7 MW
Battery Point BESS31 May 202431 Oct 203025 MW
Beinn Thulabaigh Wind7 Nov 202531 Oct 20336 MW
West Coast Community Energy7 Nov 202531 Oct 203344 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2027: 50 MW2030: 79 MW2033: 129 MW2027202820292030203120322033129 MW
0 MW100 MW200 MW2027: 50 MW2030: 79 MW2033: 129 MW2027202920312033129 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202749.7 MW
203078.9 MW
2033128.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Pentland Road4.2 MW0 MW31 Dec 20302gate 2Under Construction/Commissioning
2Druim Leathann BEGA49.7 MW4.2 MW31 Mar 2027not statedgate not printedScoping
3Battery Point BESS25 MW53.9 MW31 Oct 2030not statedgate not printedScoping
4Beinn Thulabaigh Wind6 MW78.9 MW31 Oct 2033not statedgate not printedScoping
5West Coast Community Energy44 MW84.9 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2027149.7 MW
2030229.2 MW
2033250 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Druim Leathann BEGAOnshore wind49.7 MW31 Mar 2027Scoping
West Coast Community EnergyOnshore wind44 MW31 Oct 2033Scoping
Battery Point BESSBattery storage25 MW31 Oct 2030Scoping
Stornoway (Battery Point)Thermal22.3 MWnot statedBuilt
Pentland RoadOnshore wind18 MW31 Dec 2030Under Construction/Commissioning
Beinn Thulabaigh WindOnshore wind6 MW31 Oct 2033Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.