Sussex and Romney Connection Node B 400kV Substation

NESO connection site, host NGET.

Contracted here1.67 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date21 Oct 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,665 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Shipley Road BESS31 May 202421 Oct 2031400 MW
Lightsource Shipley PV31 May 202430 Oct 2037240 MW
DRAGON GREEN BESS31 May 202431 Oct 2037300 MW
SAVE OUR PLANET21 Mar 202531 Oct 2037500 MW
Lanehurst Farm BESS22 Jul 202531 Oct 2037225 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2031: 400 MW2037: 1.7 GW20312032203320342035203620371.7 GW
0 MW1.0 GW2.0 GW2031: 400 MW2037: 1.7 GW20312033203520371.7 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2031400 MW
20371,665 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Shipley Road BESS400 MW0 MW21 Oct 2031not statedgate not printedConsents Approved
2Lightsource Shipley PV240 MW400 MW30 Oct 20371gate 1Scoping
3DRAGON GREEN BESS300 MW640 MW31 Oct 20371gate 1Scoping
4SAVE OUR PLANET500 MW940 MW31 Oct 20371gate 1Scoping
5Lanehurst Farm BESS225 MW1,440 MW31 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20311400 MW
203741,265 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
SAVE OUR PLANETHybrid500 MW31 Oct 2037Scoping
Shipley Road BESSBattery storage400 MW21 Oct 2031Consents Approved
DRAGON GREEN BESSBattery storage300 MW31 Oct 2037Scoping
Lightsource Shipley PVHybrid240 MW30 Oct 2037Scoping
Lanehurst Farm BESSBattery storage225 MW31 Oct 2037Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.