The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Shipley Road BESS
31 May 2024 to 21 Oct 2031 (gate not printed) - Lightsource Shipley PV
31 May 2024 to 30 Oct 2037 (gate 1) - DRAGON GREEN BESS
31 May 2024 to 31 Oct 2037 (gate 1) - SAVE OUR PLANET
21 Mar 2025 to 31 Oct 2037 (gate 1) - Lanehurst Farm BESS
22 Jul 2025 to 31 Oct 2037 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Shipley Road BESS | 31 May 2024 | 21 Oct 2031 | 400 MW |
| Lightsource Shipley PV | 31 May 2024 | 30 Oct 2037 | 240 MW |
| DRAGON GREEN BESS | 31 May 2024 | 31 Oct 2037 | 300 MW |
| SAVE OUR PLANET | 21 Mar 2025 | 31 Oct 2037 | 500 MW |
| Lanehurst Farm BESS | 22 Jul 2025 | 31 Oct 2037 | 225 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2031 | 400 MW |
| 2037 | 1,665 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Shipley Road BESS | 400 MW | 0 MW | 21 Oct 2031 | not stated | gate not printed | Consents Approved |
| 2 | Lightsource Shipley PV | 240 MW | 400 MW | 30 Oct 2037 | 1 | gate 1 | Scoping |
| 3 | DRAGON GREEN BESS | 300 MW | 640 MW | 31 Oct 2037 | 1 | gate 1 | Scoping |
| 4 | SAVE OUR PLANET | 500 MW | 940 MW | 31 Oct 2037 | 1 | gate 1 | Scoping |
| 5 | Lanehurst Farm BESS | 225 MW | 1,440 MW | 31 Oct 2037 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2031 | 1 | 400 MW |
| 2037 | 4 | 1,265 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| SAVE OUR PLANET | Hybrid | 500 MW | 31 Oct 2037 | Scoping |
| Shipley Road BESS | Battery storage | 400 MW | 21 Oct 2031 | Consents Approved |
| DRAGON GREEN BESS | Battery storage | 300 MW | 31 Oct 2037 | Scoping |
| Lightsource Shipley PV | Hybrid | 240 MW | 30 Oct 2037 | Scoping |
| Lanehurst Farm BESS | Battery storage | 225 MW | 31 Oct 2037 | Scoping |