N84 Grid

Tarland GSP

NESO connection site, host SHET.

Contracted here0.10 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Oct 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue104.88 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Cornabo Wind7 Nov 202531 Oct 20262.4 MW
Tarland Battery Storage System31 May 202431 Oct 202620 MW
Burnside Farm PV7 Nov 202531 Oct 203232.58 MW
Blackhill Farm7 Nov 202531 Oct 203249.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 22 MW2032: 105 MW2026202720282029203020312032105 MW
0 MW100 MW200 MW2026: 22 MW2032: 105 MW2026202820302032105 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202622.4 MW
2032104.88 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Cornabo Wind2.4 MW0 MW31 Oct 2026not statedgate not printedScoping
2Tarland Battery Storage System20 MW2.4 MW31 Oct 2026not statedgate not printedConsents Approved
3Burnside Farm PV32.58 MW22.4 MW31 Oct 20321gate 1Scoping
4Blackhill Farm49.9 MW54.98 MW31 Oct 20321gate 1Scoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026222.4 MW
2032282.48 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Blackhill FarmBattery storage49.9 MW31 Oct 2032Scoping
Burnside Farm PVSolar32.58 MW31 Oct 2032Scoping
Tarland Battery Storage SystemBattery storage20 MW31 Oct 2026Consents Approved
Kildrummy Wind FarmOnshore wind18.4 MWnot statedBuilt
Cairnmore PH3 Wind FarmOnshore wind2.55 MWnot statedBuilt
Cornabo WindOnshore wind2.4 MW31 Oct 2026Scoping
River Muick HydroHydro and pumped storage2 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.