N84 Grid

Taunton 400kV Substation

NESO connection site, host NGET.

Contracted here0.10 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Oct 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue100 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Taunton31 May 2024 to 31 Oct 2031 (gate 1)
  • Taunton31 May 2024 to 31 Oct 2037 (gate 1)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Taunton31 May 202431 Oct 203149.9 MW
Taunton31 May 202431 Oct 203750.1 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2031: 50 MW2037: 100 MW2031203220332034203520362037100 MW
0 MW50 MW100 MW2031: 50 MW2037: 100 MW2031203320352037100 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
203149.9 MW
2037100 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Taunton49.9 MW0 MW31 Oct 20311gate 1Awaiting Consents
2Taunton50.1 MW49.9 MW31 Oct 20371gate 1Awaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2031149.9 MW
2037150.1 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Taunton (PIVOTED POWER LLP)Battery storage100 MW31 Oct 2037Awaiting Consents
HuntworthGas10 MWnot statedBuilt

Supported by National Energy SO Open Data