N84 Grid

Taynuilt GSP

NESO connection site, host SHET.

Contracted here0.17 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Oct 2034Date printed in the register

The queue, in order

Order calculated by N84
First in queue173.6 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Cruach Glenamachrie Wind Farm7 Nov 202531 Oct 203450 MW
Barachander Wind Farm7 Nov 202531 Oct 203466 MW
Beinn Ghlas20 Dec 202431 Oct 203457.6 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2034: 174 MW2034174 MW
0 MW100 MW200 MW2034: 174 MW2034174 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2034173.6 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Cruach Glenamachrie Wind Farm50 MW0 MW31 Oct 2034not statedgate not printedAwaiting Consents
2Barachander Wind Farm66 MW50 MW31 Oct 20341gate 1Scoping
3Beinn Ghlas57.6 MW116 MW31 Oct 2034not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20343173.6 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Barachander Wind FarmOnshore wind66 MW31 Oct 2034Scoping
Beinn GhlasOnshore wind57.6 MW31 Oct 2034Awaiting Consents
Cruach Glenamachrie Wind FarmOnshore wind50 MW31 Oct 2034Awaiting Consents
InveraweHydro and pumped storage25 MWnot statedBuilt
Loch Etive HydroHydro and pumped storage6.8 MWnot statedBuilt
Glen Noe Hydro Generating StationHydro and pumped storage2 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.