Tealing 132kV Substation

NESO connection site, host SHET.

Contracted here2.60 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,600 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Myreton BESS21 Mar 202531 Oct 2028200 MW
Tealing Energy Park31 May 202431 Oct 20331,400 MW
Akku Tealing Battery Storage27 Sep 202431 Oct 2033500 MW
South Powrie Farm27 Sep 202431 Oct 2033500 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2028: 200 MW2033: 2.6 GW2028202920302031203220332.6 GW
0 MW2.0 GW4.0 GW2028: 200 MW2033: 2.6 GW20282030203220332.6 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028200 MW
20332,600 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Myreton BESS200 MW0 MW31 Oct 2028not statedgate not printedScoping
2Tealing Energy Park1,400 MW200 MW31 Oct 20331gate 1Scoping
3Akku Tealing Battery Storage500 MW1,600 MW31 Oct 20331gate 1Scoping
4South Powrie Farm500 MW2,100 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20281200 MW
203332,400 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Tealing Energy ParkBattery storage1,400 MW31 Oct 2033Scoping
Seagreen 1 Offshore Wind FarmOffshore wind1,075 MWnot statedBuilt
Akku Tealing Battery StorageBattery storage500 MW31 Oct 2033Scoping
South Powrie FarmBattery storage500 MW31 Oct 2033Scoping
Myreton BESSBattery storage200 MW31 Oct 2028Scoping
Isenau TwoBattery storage0 MWnot statedScoping
Isenau FiveBattery storage0 MWnot statedScoping
Tealing BESS (100MW)Battery storage0 MWnot statedScoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.