N84 Grid

Teeside Connection Node A 132kV Substation

NESO connection site, host NGET.

Contracted here1.47 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Oct 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,468 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Lackenby PV & BESS Station31 May 202431 Oct 2033240 MW
NEL Lackenby31 May 202430 Oct 2035228 MW
NatPower Teesside Green Energy Park31 May 202431 Oct 20351,000 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2033: 240 MW2035: 1.5 GW2033203420351.5 GW
0 MW1.0 GW2.0 GW2033: 240 MW2035: 1.5 GW2033203420351.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2033240 MW
20351,468 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Lackenby PV & BESS Station240 MW0 MW31 Oct 20331gate 1Scoping
2NEL Lackenby228 MW240 MW30 Oct 20351gate 1Scoping
3NatPower Teesside Green Energy Park1,000 MW468 MW31 Oct 2035not statedgate not printedConsents Approved

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20331240 MW
203521,228 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
NatPower Teesside Green Energy ParkBattery storage1,000 MW31 Oct 2035Consents Approved
Tees Renewable Energy PlantBiomass and waste285 MWnot statedBuilt
Lackenby PV & BESS StationHybrid240 MW31 Oct 2033Scoping
NEL LackenbyBattery storage228 MW30 Oct 2035Scoping

Supported by National Energy SO Open Data