N84 Grid

Teviot 400/132kV Substation

NESO connection site, host SPT.

Contracted here0.81 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 May 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue807.9 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Teviot Wind Farm31 May 2024 to 30 May 2033 (gate 1)
  • Chesters20 Dec 2024 to 29 Oct 2033 (gate not printed)
  • Cliffhope22 Jul 2025 to 31 Oct 2034 (gate 1)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Teviot Wind Farm31 May 202430 May 2033522.9 MW
Chesters20 Dec 202429 Oct 203380 MW
Cliffhope22 Jul 202531 Oct 2034205 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2033: 603 MW2034: 808 MW20332034808 MW
0 MW500 MW1.0 GW2033: 603 MW2034: 808 MW20332034808 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2033602.9 MW
2034807.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Teviot Wind Farm522.9 MW0 MW30 May 20331gate 1Scoping
2Chesters80 MW522.9 MW29 Oct 2033not statedgate not printedScoping
3Cliffhope205 MW602.9 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20332602.9 MW
20341205 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Teviot Wind FarmOnshore wind522.9 MW30 May 2033Scoping
CliffhopeHybrid205 MW31 Oct 2034Scoping
ChestersHybrid80 MW29 Oct 2033Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.