N84 Grid

Thormanby 400kV Substation

NESO connection site, host NGET.

Contracted here0.60 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date28 Oct 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue599.9 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Sedgeby Solar Farm31 May 202428 Oct 2033350 MW
Poppleton PV & BESS Sub31 May 202424 Oct 2035249.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2033: 350 MW2035: 600 MW203320342035600 MW
0 MW400 MW800 MW2033: 350 MW2035: 600 MW203320342035600 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2033350 MW
2035599.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Sedgeby Solar Farm350 MW0 MW28 Oct 20331gate 1Awaiting Consents
2Poppleton PV & BESS Sub249.9 MW350 MW24 Oct 20351gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20331350 MW
20351249.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Sedgeby Solar FarmHybrid350 MW28 Oct 2033Awaiting Consents
Poppleton PV & BESS SubHybrid249.9 MW24 Oct 2035Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.