The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Thorpe Marsh Energy Park
31 May 2024 to 30 Jan 2027 (gate 2) - Thorpe Marsh 1 (Tertiary)
31 May 2024 to 30 Oct 2028 (gate not printed) - Thorpe Marsh Green Energy Centre
31 May 2024 to 30 Oct 2030 (gate not printed) - Fenwick Solar Project
31 May 2024 to 16 Apr 2032 (gate not printed) - Thorpe Marsh Green Energy Centre
31 May 2024 to 31 Aug 2032 (gate not printed) - NEL Nicholson
31 May 2024 to 31 Oct 2035 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Thorpe Marsh Energy Park | 31 May 2024 | 30 Jan 2027 | 1,400 MW |
| Thorpe Marsh 1 (Tertiary) | 31 May 2024 | 30 Oct 2028 | 57 MW |
| Thorpe Marsh Green Energy Centre | 31 May 2024 | 30 Oct 2030 | 400 MW |
| Fenwick Solar Project | 31 May 2024 | 16 Apr 2032 | 237.5 MW |
| Thorpe Marsh Green Energy Centre | 31 May 2024 | 31 Aug 2032 | 625 MW |
| NEL Nicholson | 31 May 2024 | 31 Oct 2035 | 180 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 1,400 MW |
| 2028 | 1,457 MW |
| 2030 | 1,857 MW |
| 2032 | 2,719.5 MW |
| 2035 | 2,899.5 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Thorpe Marsh Energy Park | 1,400 MW | 0 MW | 30 Jan 2027 | 2 | gate 2 | Under Construction/Commissioning |
| 2 | Thorpe Marsh 1 (Tertiary) | 57 MW | 1,400 MW | 30 Oct 2028 | not stated | gate not printed | Consents Approved |
| 3 | Thorpe Marsh Green Energy Centre | 400 MW | 1,457 MW | 30 Oct 2030 | not stated | gate not printed | Awaiting Consents |
| 4 | Fenwick Solar Project | 237.5 MW | 1,857 MW | 16 Apr 2032 | not stated | gate not printed | Scoping |
| 5 | Thorpe Marsh Green Energy Centre | 625 MW | 2,094.5 MW | 31 Aug 2032 | not stated | gate not printed | Awaiting Consents |
| 6 | NEL Nicholson | 180 MW | 2,719.5 MW | 31 Oct 2035 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 1 | 1,400 MW |
| 2028 | 1 | 57 MW |
| 2030 | 1 | 400 MW |
| 2032 | 2 | 862.5 MW |
| 2035 | 1 | 180 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Thorpe Marsh Energy Park | Battery storage | 1,400 MW | 30 Jan 2027 | Under Construction/Commissioning |
| Thorpe Marsh Green Energy Centre | Hybrid | 1,025 MW | 31 Aug 2032 | Awaiting Consents |
| Fenwick Solar Project | Hybrid | 237.5 MW | 16 Apr 2032 | Scoping |
| NEL Nicholson | Battery storage | 180 MW | 31 Oct 2035 | Scoping |
| Thorpe Marsh 1 (Tertiary) | Hybrid | 57 MW | 30 Oct 2028 | Consents Approved |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.