N84 Grid

THURSO 2 275/33KV GRID SUPPLY POINT SUBSTATION

NESO connection site, host SHET.

Contracted here0.14 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Oct 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue144.3 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Glengolly7 Nov 202531 Oct 203349.9 MW
Geiselittle BESS7 Nov 202531 Oct 203349.9 MW
Swarclett Farm and BESS7 Nov 202531 Oct 203318 MW
Olrig Mains Wind Farm7 Nov 202531 Oct 203326.5 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2033: 144 MW2033144 MW
0 MW100 MW200 MW2033: 144 MW2033144 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2033144.3 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Glengolly49.9 MW0 MW31 Oct 20331gate 1Scoping
2Geiselittle BESS49.9 MW49.9 MW31 Oct 2033not statedgate not printedScoping
3Swarclett Farm and BESS18 MW99.8 MW31 Oct 20331gate 1Scoping
4Olrig Mains Wind Farm26.5 MW117.8 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20334144.3 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Geiselittle BESSBattery storage49.9 MW31 Oct 2033Scoping
GlengollyBattery storage49.9 MW31 Oct 2033Scoping
Olrig Mains Wind FarmOnshore wind26.5 MW31 Oct 2033Scoping
Swarclett Farm and BESSHybrid18 MW31 Oct 2033Scoping

Supported by National Energy SO Open Data