N84 Grid

Thurso South 132/33kV GSP Substation

NESO connection site, host SHET.

Contracted here1.06 GWNot yet connected, as printed
Entries in the queue8entries with a printed MW
Earliest connection date30 Jun 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue356.1 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Thurso BESS7 Nov 202530 Jun 202749.9 MW
Cairnmore Hill Wind Farm31 May 202431 May 202836 MW
Buckies Farm BESS7 Nov 202530 Oct 203050 MW
Thurso South BESS31 May 202431 Oct 2030100 MW
Farm 100MW BESS27 Sep 202431 Oct 2033100 MW
Lochend Extension7 Nov 202530 Apr 203420.2 MW
Mybster 2 Battery Storage20 Dec 202431 Oct 2034500 MW
Lythmore22 Jul 202531 Oct 2034200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2027: 50 MW2028: 86 MW2030: 236 MW2033: 336 MW2034: 1.1 GW202720282029203020312032203320341.1 GW
0 MW1.0 GW2.0 GW2027: 50 MW2028: 86 MW2030: 236 MW2033: 336 MW2034: 1.1 GW20272029203120341.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202749.9 MW
202885.9 MW
2030235.9 MW
2033335.9 MW
20341,056.1 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Thurso BESS49.9 MW0 MW30 Jun 20272gate 2Scoping
2Cairnmore Hill Wind Farm36 MW49.9 MW31 May 2028not statedgate not printedAwaiting Consents
3Buckies Farm BESS50 MW85.9 MW30 Oct 20301gate 1Scoping
4Thurso South BESS100 MW135.9 MW31 Oct 20301gate 1Scoping
5Farm 100MW BESS100 MW235.9 MW31 Oct 20331gate 1Scoping
6Lochend Extension20.2 MW335.9 MW30 Apr 20341gate 1Scoping
7Mybster 2 Battery Storage500 MW356.1 MW31 Oct 2034not statedgate not printedScoping
8Lythmore200 MW856.1 MW31 Oct 2034not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2027149.9 MW
2028136 MW
20302150 MW
20331100 MW
20343720.2 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Mybster 2 Battery StorageBattery storage500 MW31 Oct 2034Scoping
LythmoreHybrid200 MW31 Oct 2034Scoping
Thurso South BESSBattery storage100 MW31 Oct 2030Scoping
Farm 100MW BESSBattery storage100 MW31 Oct 2033Scoping
Buckies Farm BESSBattery storage50 MW30 Oct 2030Scoping
Thurso BESSBattery storage49.9 MW30 Jun 2027Scoping
Cairnmore Hill Wind FarmOnshore wind36 MW31 May 2028Awaiting Consents
Lochend ExtensionOnshore wind20.2 MW30 Apr 2034Scoping
Lochend Wind FarmOnshore wind9.2 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.