Tod Point 275kV Substation

NESO connection site, host NGET.

Contracted here0.86 GWNot yet connected, as printed
Entries in the queue1entry with a printed MW
Earliest connection date30 Jul 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue860 MW across the first project
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Net Zero Teesside Power Project31 May 202430 Jul 2027860 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2027: 860 MW2027860 MW
0 MW500 MW1.0 GW2027: 860 MW2027860 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027860 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Net Zero Teesside Power Project860 MW0 MW30 Jul 2027not statedgate not printedConsents Approved

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20271860 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Net Zero Teesside Power ProjectGas860 MW30 Jul 2027Consents Approved

Supported by National Energy SO Open Data