Trent Valley North Connection Node B 400kV Substation

NESO connection site, host NGET.

Contracted here1.69 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date30 Oct 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,690 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Tween Bridge Solar Park31 May 202430 Oct 2029340 MW
Tween Bridge Solar Park31 May 202430 Nov 2032250 MW
Kinoulton Solar & BESS20 Dec 202430 Oct 2034500 MW
Epworth PV & BESS Station31 May 202430 Oct 2035150 MW
Tween Bridge Solar Park31 May 202430 Oct 2037210 MW
CRT Keadby 222 Jul 202530 Oct 2039240 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2029: 340 MW2032: 590 MW2034: 1.1 GW2035: 1.2 GW2037: 1.5 GW2039: 1.7 GW2029203120332035203720391.7 GW
0 MW1.0 GW2.0 GW2029: 340 MW2032: 590 MW2034: 1.1 GW2035: 1.2 GW2037: 1.5 GW2039: 1.7 GW20292032203520391.7 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029340 MW
2032590 MW
20341,090 MW
20351,240 MW
20371,450 MW
20391,690 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Tween Bridge Solar Park340 MW0 MW30 Oct 2029not statedgate not printedScoping
2Tween Bridge Solar Park250 MW340 MW30 Nov 2032not statedgate not printedScoping
3Kinoulton Solar & BESS500 MW590 MW30 Oct 20341gate 1Scoping
4Epworth PV & BESS Station150 MW1,090 MW30 Oct 20351gate 1Scoping
5Tween Bridge Solar Park210 MW1,240 MW30 Oct 2037not statedgate not printedScoping
6CRT Keadby 2240 MW1,450 MW30 Oct 20391gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20291340 MW
20321250 MW
20341500 MW
20351150 MW
20371210 MW
20391240 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Tween Bridge Solar ParkHybrid800 MW30 Oct 2037Scoping
Kinoulton Solar & BESSHybrid500 MW30 Oct 2034Scoping
CRT Keadby 2Battery storage240 MW30 Oct 2039Scoping
Epworth PV & BESS StationHybrid150 MW30 Oct 2035Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.