N84 Grid

Trent Valley South Connection Node C 400kV Substation

NESO connection site, host NGET.

Contracted here5.39 GWNot yet connected, as printed
Entries in the queue11entries with a printed MW
Earliest connection date30 Oct 2034Date printed in the register

The queue, in order

Order calculated by N84
First in queue3,140 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Coddington31 May 202430 Oct 2034240 MW
Bicker Fen22 Jul 202530 Oct 2034400 MW
Oak Holt Solar20 Dec 202430 Oct 2034400 MW
Elmya Foxdale BESS20 Dec 202430 Oct 2034800 MW
Cranwell Solar & BESS Farm21 Mar 202530 Oct 2034300 MW
NatPower Navenby Energy Park20 Dec 202430 Oct 20341,000 MW
Grantham Solar Farm - RSL21 Mar 202530 Oct 2034810 MW
Barnby Solar Farm31 May 202431 Oct 2034249.9 MW
Grantham Generation31 May 202430 Oct 2035700 MW
Noventum Navenby31 May 202430 Oct 2035249 MW
Kinder PV & BESS Station22 Jul 202530 Oct 2039240 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW4.0 GW8.0 GW2034: 4.2 GW2035: 5.1 GW2039: 5.4 GW2034203520362037203820395.4 GW
0 MW4.0 GW8.0 GW2034: 4.2 GW2035: 5.1 GW2039: 5.4 GW20342036203820395.4 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20344,199.9 MW
20355,148.9 MW
20395,388.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Coddington240 MW0 MW30 Oct 20341gate 1Scoping
2Bicker Fen400 MW240 MW30 Oct 20341gate 1Scoping
3Oak Holt Solar400 MW640 MW30 Oct 20341gate 1Scoping
4Elmya Foxdale BESS800 MW1,040 MW30 Oct 20341gate 1Scoping
5Cranwell Solar & BESS Farm300 MW1,840 MW30 Oct 2034not statedgate not printedScoping
6NatPower Navenby Energy Park1,000 MW2,140 MW30 Oct 20341gate 1Scoping
7Grantham Solar Farm - RSL810 MW3,140 MW30 Oct 20341gate 1Scoping
8Barnby Solar Farm249.9 MW3,950 MW31 Oct 2034not statedgate not printedScoping
9Grantham Generation700 MW4,199.9 MW30 Oct 20351gate 1Scoping
10Noventum Navenby249 MW4,899.9 MW30 Oct 2035not statedgate not printedScoping
11Kinder PV & BESS Station240 MW5,148.9 MW30 Oct 2039not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203484,199.9 MW
20352949 MW
20391240 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
NatPower Navenby Energy ParkBattery storage1,000 MW30 Oct 2034Scoping
Grantham Solar Farm - RSLHybrid810 MW30 Oct 2034Scoping
Elmya Foxdale BESSBattery storage800 MW30 Oct 2034Scoping
Grantham GenerationHybrid700 MW30 Oct 2035Scoping
Oak Holt SolarHybrid400 MW30 Oct 2034Scoping
Bicker FenHybrid400 MW30 Oct 2034Scoping
Cranwell Solar & BESS FarmHybrid300 MW30 Oct 2034Scoping
Barnby Solar FarmHybrid249.9 MW31 Oct 2034Scoping
Noventum NavenbyHybrid249 MW30 Oct 2035Scoping
Kinder PV & BESS StationHybrid240 MW30 Oct 2039Scoping
CoddingtonBattery storage240 MW30 Oct 2034Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.