The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Stoke Bardolph
31 May 2024 to 30 Oct 2034 (gate 1) - Stoke Bardolph
31 May 2024 to 31 Oct 2034 (gate not printed) - Bute Hydrogen Project 1
31 May 2024 to 30 Oct 2035 (gate 1) - Noventum - Budby
20 Dec 2024 to 30 Oct 2035 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Stoke Bardolph | 31 May 2024 | 30 Oct 2034 | 240 MW |
| Stoke Bardolph | 31 May 2024 | 31 Oct 2034 | 1,000 MW |
| Bute Hydrogen Project 1 | 31 May 2024 | 30 Oct 2035 | 4,800 MW |
| Noventum - Budby | 20 Dec 2024 | 30 Oct 2035 | 380 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2034 | 1,240 MW |
| 2035 | 6,420 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Stoke Bardolph | 240 MW | 0 MW | 30 Oct 2034 | 1 | gate 1 | Scoping |
| 2 | Stoke Bardolph | 1,000 MW | 240 MW | 31 Oct 2034 | not stated | gate not printed | Scoping |
| 3 | Bute Hydrogen Project 1 | 4,800 MW | 1,240 MW | 30 Oct 2035 | 1 | gate 1 | Scoping |
| 4 | Noventum - Budby | 380 MW | 6,040 MW | 30 Oct 2035 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2034 | 2 | 1,240 MW |
| 2035 | 2 | 5,180 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Bute Hydrogen Project 1 | Gas | 4,800 MW | 30 Oct 2035 | Scoping |
| Stoke Bardolph | Hybrid | 1,000 MW | 31 Oct 2034 | Scoping |
| Noventum - Budby | Hybrid | 380 MW | 30 Oct 2035 | Scoping |
| Stoke Bardolph | Battery storage | 240 MW | 30 Oct 2034 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.