N84 Grid

Walham 400kV Substation

NESO connection site, host NGET.

Contracted here0.95 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date17 Nov 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue949 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Walham PV & BESS Sub31 May 202417 Nov 2033249 MW
Walham 700MW BESS31 May 202417 Nov 2033700 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2033: 949 MW2033949 MW
0 MW500 MW1.0 GW2033: 949 MW2033949 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2033949 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Walham PV & BESS Sub249 MW0 MW17 Nov 20331gate 1Scoping
2Walham 700MW BESS700 MW249 MW17 Nov 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20332949 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Walham 700MW BESSBattery storage700 MW17 Nov 2033Scoping
Walham PV & BESS SubHybrid249 MW17 Nov 2033Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.