The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Walham PV & BESS Sub
31 May 2024 to 17 Nov 2033 (gate 1) - Walham 700MW BESS
31 May 2024 to 17 Nov 2033 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Walham PV & BESS Sub | 31 May 2024 | 17 Nov 2033 | 249 MW |
| Walham 700MW BESS | 31 May 2024 | 17 Nov 2033 | 700 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2033 | 949 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Walham PV & BESS Sub | 249 MW | 0 MW | 17 Nov 2033 | 1 | gate 1 | Scoping |
| 2 | Walham 700MW BESS | 700 MW | 249 MW | 17 Nov 2033 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2033 | 2 | 949 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Walham 700MW BESS | Battery storage | 700 MW | 17 Nov 2033 | Scoping |
| Walham PV & BESS Sub | Hybrid | 249 MW | 17 Nov 2033 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.