N84 Grid

Wallend 400kV Substation

NESO connection site, host NGET.

Contracted here2.90 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date7 Jul 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,900 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
NeuConnect Interconnector15 Feb 20227 Jul 20271,400 MW
Nautilus15 Feb 202231 Oct 20291,500 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2027: 1.4 GW2029: 2.9 GW2027202820292.9 GW
0 MW2.0 GW4.0 GW2027: 1.4 GW2029: 2.9 GW2027202820292.9 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20271,400 MW
20292,900 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1NeuConnect Interconnector1,400 MW0 MW7 Jul 20272gate 2Under Construction/Commissioning
2Nautilus1,500 MW1,400 MW31 Oct 2029not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Interconnector Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202711,400 MW
202911,500 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
NautilusInterconnector1,500 MW31 Oct 2029Scoping
NeuConnect InterconnectorInterconnector1,400 MW7 Jul 2027Under Construction/Commissioning

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.